Completed Projects from Previous Years

Water Projects

Completed in FY2017-2018

Replaced over 19,000 linear feet of water lines:

  • Candyce
  • US HWY 77 East Side of Moonlight Drive to Fidelity Bank
  • Lawndale
  • Greenbriar
  • Dean
  • Dison
  • Stefka
  • Mclendon
  • Loop 340
  • Caron
  • Donlo
  • Ward Highway 77 to Andrews

Well Site Improvements:

  • Replaced pump houses at 4 well sites
  • Updated piping and added new electrical and SCADA controls.
  • A new 250,000-gallon ground storage tank was added to 1 of the well sites.
  • Elevated Water Storage Improvements
  • Installed a 3rd booster pump which pumps water to the upper-pressure plane.
  • Installed a new generator to provide service during power outages.

Water Treatment Plant Improvements:

  • Cleaned sediment out of intake structure
  • Installed a new pump that pumps 5,100 gallons of water per minute.
  • Completed Micro-Floc rehab project.
  • Installation of new membranes.
  • Removed vegetation in the area where the new reservoir will be constructed.

Wastewater Projects

Completed in FY 2017-2018

Replaced old clay pipe sewer mains at the following:

  • Stefka
  • Dison
  • Hillview
  • Nelson
  • Ivan
  • Moonlight
  • Ward

Enhanced monitoring capabilities of our lift stations by adding a SCADA system at our larger sites:

  • South Pond (Valley View area)
  • Moonlight
  • Industrial (Sun Valley)
  • Lux
  • Dayton Street

Reduced the number of operating lift stations by taking two out of service (a goal every wastewater system has):

  • Sturgis
  • Ivan
  • Lux lift station was relocated and replaced.

Replacement of mains in a few areas/sections of:

  • A few areas of Fain Estates
  • Andrews
  • McLendon
  • Replacement of sewer mains in Meadowbrook Addition.

Projects to increase flow in areas:

  • Installed new gravity sewer lines to allow abandonment of the Lyndale lift station.
  • Replacement of sewer mains in Meadowbrook Addition.
  • Sewer Line Extension across Lyndale & Tate Project
  • The City partnered with a developer to install an 18-inch sewer line across Lyndale and Tate. This partnership saved the City around $150,000 and is the 2nd step in re-routing the flow on the South Pond Lift Station. By re-routing the flow, it increases the capacity for new development and reduces some of the sewer issues around town.

Streets Projects

Completed in FY2017-2018

Chip Seal:

  • Downsville
  • Hoffmeyer
  • South Old Robinson Road
  • Tate Street
  • Peggy
  • West Tate/Hoffmeyer (from Pompano Park Drive to Greig Drive)
  • South Old Robinson Road (from Highway 77 to Castleman Creek)
  • Downsville Road (from Hobbs Lane to a little past Hobbs Lane)
  • Lux Drive
  • Brint Lane
  • Georgia Lane
  • Crack Seal
  • San Bonito Drive
  • Violet Drive
  • Hawkins Court
  • Ranch Drive
  • A portion of Dale Drive
  • Karnes (from Highway 77 to North Old Robinson Road)
  • Cedar Ridge Circle
  • Surrey Ridge Addition

Crack Seal:

  • San Bonito Drive
  • Violet Drive
  • Hawkins Court
  • Ranch Drive
  • A portion of Dale Drive
  • Karnes (from Highway 77 to North Old Robinson Road)
  • Cedar Ridge Circle
  • Surrey Ridge Addition